THE SHORT ANSWER

Check whether the request fixes a mistake, uses an agreed revision or adds something new. For extra scope, explain the change and its effect on price or timing before doing the work. Offer a concrete choice and get the agreed change recorded through the contract's change process.

The message arrives just as you are finishing: “Could you add one more page? It should be quick.” You want to keep the relationship, but another unpaid evening is not what you priced.

Do not begin by arguing about whether it is small. Find the agreed deliverable and work out which kind of request this is. Scope creep is a useful name for expanding work, but it is not a substitute for explaining the difference.

Sort the request before pricing it

These fictional design-project examples show three different situations:

Request What to check A reasonable starting response
Fix a broken link you were supposed to configure Does the delivered work meet the agreed requirement? Correct the delivery issue; do not label it extra scope merely because it takes time
Change a colour during one of two included revision rounds Is this within the agreed revision process and original direction? Confirm which included round it uses
Add a booking system to a brochure website Was booking functionality included anywhere in the scope? Explain the additional deliverable and offer a change quote

A request can sit between categories. If the scope says “booking page,” both of you may have understood something different. Clarify whether that meant a contact form or a live scheduling integration before declaring the client wrong.

Point to the agreement without turning it into a confrontation

Gather the accepted proposal, scope, relevant messages and change procedure. Check who may approve additional work and whether a particular written form is required. Do not assume that the person sending feedback can approve a budget increase.

The NYC freelance model agreement is one practical example of recording services and compensation explicitly. Its local context does not make its requirements universal; the useful habit is to connect the request to the work and price actually agreed.

Write the difference in a sentence: “The agreed scope covers five informational pages; this request adds appointment selection, availability and confirmation emails.” That is clearer than “This is scope creep.”

Offer a choice the client can approve

Use an add, swap or defer response. These are fictional examples:

Add the work: “I can add the booking integration for an additional $300, with delivery moving from Friday to Tuesday. That includes setup and one test booking. Please confirm through the change-order process before I begin.”

Swap within the budget: “If keeping the current budget is the priority, we could replace the planned gallery page with a simpler booking enquiry form. It would collect requests rather than show live availability. Would that meet the need?”

Defer the change: “We can launch the agreed pages on Friday and quote the booking system as a second phase. That keeps the current launch date.”

Make the alternatives meaningfully different. Do not offer the same work for free under a different label. If you choose to include a small courtesy change, identify what you are including and avoid suggesting that every later addition is also included.

Show the effect on the whole project

A five-minute visible change may require testing, new content or another person's approval. List those dependencies without inflating them. A useful change note contains:

  • The additional or replacement deliverable.
  • The price and whether any third-party fees are separate.
  • The revised date and what you need from the client.
  • What remains included, and who will approve completion.

For example, “$300 for setup” does not answer whether the booking provider's subscription is included. Surface that before approval, not on the next invoice.

If you already did the extra work

Do not manufacture retrospective approval. Explain what happened, identify the additional work and ask how to resolve it. Separate work the client expressly approved from work you chose to do without discussing the price.

You can still set a clear process for future requests: “Before I take on the next change, I'll send its scope, cost and timing for approval.” Whether an existing disputed amount is payable depends on the agreement and applicable law; a new invoice alone does not settle that question.

If you want help locating the scope and change provisions, Contracts.money can review your PDF or DOCX with the request described in context and email an AI analysis. It does not approve the change, estimate your actual effort or negotiate with the client.

For the earlier stage, use the freelance-contract checklist. For more ways to word a request, see clarification emails that name the issue clearly.

Put your own contract in context.

PDF or DOCX. Your priorities. An AI review delivered by email.

Review my contract · $1